A reglet is a groove cut or cast into a wall, or a metal receiver fixed to it, that holds the top edge of a counterflashing where a roof meets a wall, parapet or chimney.

6 min read4 sourcesNorth AmericaEurope
Cite this entry"Reglet." roof.wiki. https://roof.wiki/reglet/ (accessed 2026-11-03).
Function
Receives and secures the top edge of a counterflashing
Types
Cut-in (sawn/raked), cast-in, masonry/stucco, surface-mounted, two-part snap-in
Depth in masonry (US guidance)
2-2-1/2 in (50-64 mm); about 1 in (25 mm) in stone
UK lead chase depth
At least 25 mm (1 in), fixings about 450 mm apart
Counterflashing lap over base flashing
At least 3-4 in (75-100 mm)
Common materials
16 oz copper, G90 galvanised steel, 3003 aluminium, 304 stainless, lead (UK)
Other names
Raggle (US), chase (UK)

A reglet is the slot that holds the upper edge of a counterflashing where a roof meets a vertical surface. It may be a groove sawn or raked into masonry, a slot cast into concrete, or a formed metal channel built into or fixed onto the wall. The counterflashing's horizontal flange is turned into the reglet and secured, and its vertical leg hangs down over the top of the roof's base flashing, shedding water that runs down the wall past the joint.12 In older American usage the groove is also called a raggle,1 and in British leadwork the equivalent groove in brickwork is usually called a chase.4

The reglet is one part of a two-part roof flashing arrangement. The base flashing turns up from the roof membrane or roof covering against the wall; the counterflashing, held by the reglet, covers the top of the base flashing. Because the two pieces are separate, the building and the roof can move independently, and the roof can later be replaced without disturbing the wall.13

Structural deckVapour control layerInsulationCover boardWaterproof membrane Hot-air welding fuses overlapping sheets into one continuous skin
Inside a flat roof

Types of reglet

Cut-in (sawn or raked) reglets

The most common reglet on existing buildings is a groove made in a horizontal mortar joint, either by raking out mortar or by sawing. On sloping roofs the cuts are made in successive bed joints to form a stepped line, and the counterflashing is cut to match (see step flashing and chimney flashing).1 Guidance in Professional Roofing recommends a reglet depth of 2 to 2-1/2 in (50-64 mm) in mass masonry, or 1-3/4 to 2 in (44-50 mm) where equipment limits it, and about 1 in (25 mm) where a reglet has to be cut directly into stone.1 The Copper Development Association likewise shows raked joints at least 2 in (50 mm) deep and notes that saw cuts make inside corners and other end conditions difficult to detail.2 Continuous reglets running parallel to a sloping roof across brick faces, and vertical reglets, are best avoided because they expose the brick body to water.1

In British practice, mortar is raked out to a depth of at least 25 mm (1 in) for lead flashings, with joints at least 6 mm (1/4 in) wide; the lead is held by clips or wedges at about 450 mm (18 in) centres and in individual lengths of no more than 1.5 m (5 ft).4

Cast-in reglets

On concrete walls and parapets the reglet can be formed while the concrete is poured, either by casting a groove or by setting a preformed metal reglet into the formwork. Proprietary cast-in reglets are typically made of 26 gauge galvanised steel and arrive with a temporary cover so that concrete does not fill the slot.3 The Copper Development Association shows both a reglet cut or cast into concrete and a copper receiver cast into the wall to take a cap flashing.2

Masonry and stucco reglets

Metal reglets can also be built into a masonry bed joint as the wall goes up, or set into a stucco or render finish. A copper receiver laid between masonry courses, for example, holds the edge of the exposed flashing.2 Proprietary masonry and stucco reglets are commonly 24 gauge galvanised steel.3

Surface-mounted reglets

Where the wall cannot be cut — on panels, render, existing concrete or where cutting is impractical — a surface-mounted reglet is fastened to the face of the wall with screws or anchors, and its top edge is sealed to the wall with a sealant fillet. Surface-mounted and stucco types are installed as the walls are built or finished; concrete and masonry types can be installed during construction or sawcut and fitted afterwards.3 A surface-mounted reglet depends entirely on its top sealant joint, so it needs more maintenance than a reglet set into the wall.

Two-part (receiver and snap-in) systems

Many modern reglets are two-piece: the reglet or receiver stays in the wall, and a separate counterflashing snaps or hooks into it after the roofing is finished. The counterflashing can then be removed and reused when the roof is replaced.3 This is the same principle as the copper receiver detail.2

Materials

Reglets and counterflashings are made in a metal compatible with the flashing and nearby metals (see galvanic corrosion):13

  • Copper — 16 oz/ft2 (about 0.55 mm) cold-rolled copper to ASTM B370 is the usual minimum for counterflashing; 16 oz soft temper is easier to work into rough-faced masonry (see ASTM B370).123
  • Galvanised steel — ASTM A653 with a G90 coating, typically 24-26 gauge.3
  • Aluminium — 3003-H14 alloy around 0.025 in (0.64 mm), often prepainted.3
  • Stainless steel — Type 304 around 0.020 in (0.51 mm).3
  • Lead — the traditional British material, fixed into chases; American restoration guidance advises against new lead counterflashing because of toxicity, creep and fatigue cracking.14 Lead-coated copper has been largely unavailable since about 2011; tin-zinc coated copper is a substitute.1

Installation

A typical sequence for a cut-in reglet is:123

  1. Set the line of the reglet high enough above the roof: one guide specification places the top of the reglet at least 7 in (178 mm) above the high point of the cant strip.3
  2. Cut or rake the groove to full depth, slightly deeper than the flashing flange — one specification asks for about 1/4 in (6 mm) more than the reglet's back leg.3
  3. Insert the flange of the counterflashing (or a metal reglet) and secure it with lead wedges — at least two per piece at about 12 in (300 mm) centres in one guide, and no more than 24 in (600 mm) apart in another — or with spring clips.13
  4. Fill the joint. Mortar fill behind and over the flange, at least 3/4-1 in (19-25 mm) thick, is preferred because it lets the masonry dry outward; sealant, if used, is limited to the outer part of the joint after the mortar has cured.1 Other details fill the reglet with sealant after wedging, and British practice uses a lead pointing sealant at least 10 mm (3/8 in) deep.24
  5. Lap the counterflashing pieces — at least 4 in (100 mm) at end laps in restoration guidance, or at least 6 in (150 mm) for snap-in systems to allow for expansion.13
  6. Check the cover — the counterflashing should lap the base flashing by at least 3 to 4 in (75-100 mm), stopping about 1/2 to 1 in (13-25 mm) above the roof surface so that it does not rest on or trap water against the roofing.12

Failure modes

Common problems recorded in roof investigations include:1

  • reglets that are too shallow, cut too low, or cut through the existing base flashing;
  • reglets sloping inward, or ledges that hold water and lead it into the wall;
  • exposed fasteners sealed only with sealant, which eventually fails;
  • insufficient laps between pieces, and missing hook dams or incomplete flanges at corners;
  • counterflashing hanging lower than the piece above and trapping debris;
  • deteriorated mortar and cracked masonry above the reglet, which let so much water into the wall that it bypasses the flashing altogether.

The last point matters because a reglet only protects the joint below it. Where a wall is porous, a parapet or chimney may also need through-wall flashing or a coping, and snap-in systems require through-wall flashing to occur at or above the reglet.3

Where reglets are used

Reglets are standard wherever a low-slope membrane or a pitched roof covering meets a masonry or concrete wall: parapets, penthouse walls, chimneys and abutments. They are used with every membrane type, from built-up roofing to single-ply, and with metal and slate roofs on historic buildings, where copper counterflashing in stepped reglets is the usual restoration detail.12 In the UK and Ireland, lead flashings dressed into chases in brickwork serve the same role on houses and are covered by lead sheet guidance (see lead roofing).4

head lap Rafter + battens Slates hang in courses from the eave up.Each is nailed (or hooked) to a batten andreaches two courses up, so there are alwaysat least two thicknesses over the roof.
How slates are fixed

Sources

Reviewed 2 November 2026 · 4 sources · 4 cited inline · Editorial policy · Plain-text version · Suggest a correction

  1. Anatomy of a regleted counterflashingProfessional Roofing (NRCA) · professionalroofing.net
  2. Counterflashing (Architecture Design Handbook 9.2)Copper Development Association · copper.org
  3. Section 07710 Reglet Flashing Systems Guide SpecificationsFry Reglet via BuildSite · buildsite.com
  4. BLM Rolled Lead Sheet: Fixing FlashingsBritish Lead via SpecifiedBy · specifiedby.com

From the community

Know this topic first-hand? Share a photo you took, a correction with a source, or local knowledge. Every contribution is reviewed before it appears.

Contribute to Reglet

Loading…