Roof Expansion Joint

Also known as roof expansion joint cover · bellows expansion joint · area divider · roof movement joint · curbed expansion joint

A flexible, weatherproof break in a roof over a structural expansion joint, using raised curbs with bellows or metal covers, or a low-profile membrane loop, so the building can move without tearing the roof.

6 min read6 sourcesNorth AmericaGlobal
Cite this entry"Roof Expansion Joint." roof.wiki. https://roof.wiki/roof-expansion-joint/ (accessed 2026-11-03).
Main types
Curbed (raised) and low-profile
Raised joint height
At least 8 in (200 mm) above the roof
Structural gap
Typically at least 1 in (25 mm), roof to foundation
Area divider spacing (attached membranes)
Every 150–200 ft (46–61 m)
Example bellows
0.060 in EPDM or neoprene, 4–12 in standard widths
Control joints
No longer recommended

A roof expansion joint is a weatherproof, flexible break in a roof that lets two parts of a building move independently without tearing the roof membrane. It sits over a structural expansion joint, a continuous gap through the building's frame, and is covered by a flexible bellows, a loop of membrane or a sliding metal cover that can stretch, compress and shear as the structure moves with temperature, settlement, wind or earthquakes.12 Roof expansion joints are found mainly on large low-slope roofs of commercial, industrial and institutional buildings, where long runs of steel or concrete structure move by measurable amounts between seasons.

Structural deckVapour control layerInsulationCover boardWaterproof membrane Hot-air welding fuses overlapping sheets into one continuous skin
Inside a flat roof

Expansion joints are one of three kinds of roof joint. Area dividers are raised double nailers or curbs with no opening between them, used to break a large roof into separate membrane areas and relieve stress at re-entrant corners, but they do not accommodate structural movement. Membrane control joints, simple breaks in the membrane covered with a flexible strip, were once common but are no longer recommended: a Canadian roofing contractors' bulletin judged that they offered more potential harm than benefit, and cumulative shrinkage of bituminous membranes was found to pull them open.12 Expansion joints also differ from base flashing and roof curbs, although raised expansion joints are built and flashed very like a curb.

Where expansion joints are needed

The building's structural engineer decides where the structure is separated; the roof joint must follow every structural joint. In addition, roofing guidance calls for expansion joints or area dividers where movement is likely to concentrate:12

  • at all structural expansion joints;
  • where the deck material changes, for example from steel deck to concrete;
  • where structural framing, beams or deck change span direction;
  • where an addition meets an existing building;
  • at the junctions of wings in L-, T- and U-shaped buildings;
  • where interior temperature conditions differ sharply, such as a heated office next to an unheated warehouse;
  • at canopies and over the end joints of simply supported beams and deck units.12

On attached membrane systems, area dividers are commonly placed every 150 to 200 ft (46 to 61 m) between structural expansion joints, and at re-entrant corners.2 Building size is the most important factor in whether joints are needed.1 NRCA guidance, as excerpted in one curb manufacturer's specification, recommends expansion joints at the junctions of wings, where the deck changes direction on buildings 150 ft (46 m) or longer, and on any building longer than 200 ft (61 m), and advises against U-shaped metal expansion joints on roofs.6

The structural gap itself is typically at least 1 in (25 mm) wide and runs from roof to foundation, with doubled columns and beams on each side.2

Types

Curbed (raised) expansion joints

The traditional and most widely recommended form raises the joint on a curb on each side of the gap so that water drains away from it rather than across it. Guidance published in Building Enclosure calls for raised joints at all building expansion joints regardless of membrane type, set at least 8 in (200 mm) above the roof surface; with 3 in (75 mm) of insulation, for example, this means at least a 2×12 timber curb nailer on each side, fixed to a 2×4 horizontal nailer fastened to the deck at 24 in (610 mm) centres, with a 45° cant on the roof side and the top outer edge chamfered to shed water.2 Roof joints are also commonly built from parallel 2×8 or 2×10 timbers set on edge across the roof, flashed on their outer faces and capped with a manufactured cover.3 Prefabricated expansion curbs are also available: one system is made in 16 ft (4.9 m) sections of 13- or 14-gauge galvanised steel with 1.5 in (38 mm) glass-fibre insulation, a factory-fitted wood nailer and factory-made corners, rising 8 in (200 mm) above the finished roof.6 The US Veterans Affairs specification similarly requires expansion joint base flashing to end at least 200 mm (8 in) above the roof.4

The joint is then closed with one of:

  • a prefabricated bellows cover, a flexible rubber membrane supported by closed-cell foam to form a bellows, bonded to two metal flanges that are fixed to the curb tops and stripped in or counterflashed. One such product line uses 0.060 in (1.52 mm) EPDM or neoprene bellows, foam supports 0.375 to 0.75 in (9.5 to 19 mm) thick, and flanges of 0.032 in aluminium, 16 oz copper, 26-gauge galvanised steel or 0.018 in stainless steel; standard bellows widths are 4 to 12 in (100 to 300 mm), with special sizes up to 54 in (1.37 m), supplied in 10 ft, 50 ft and 100 ft (3, 15 and 30 m) lengths, with factory-made intersections.5
  • a sheet-metal cover, such as 24-gauge galvanised steel with a standing seam or continuous cleat that allows movement, following NRCA and SMACNA details.2 One federal specification calls for 3,000 mm (10 ft) cover lengths with fastener slots at no more than 600 mm (24 in) centres, a neoprene waterstop at least 0.8 mm (0.032 in) thick, corner legs at least 300 mm (12 in) long and 6 mm (1/4 in) gaps at end joints.4

Low-profile expansion joints

On flexible single-ply roofs of EPDM, PVC or TPO, a low-profile joint can be formed by letting a slack loop of membrane hang into the gap in the deck, supported by a compressible backer rod, and covering it with a strip of roofing membrane.3 Low-profile joints avoid curbs that obstruct drainage or traffic, but some authorities caution that roof-level joints are a failure risk even with elastomeric and thermoplastic membranes, and that joints without proper curbs lead to splits.2 Prefabricated bellows covers are also made in cant-mounted, curb-to-curb and curb-to-wall styles.5

Roof-to-wall joints

Where a low roof meets the wall of a taller building that moves independently, a curbed joint is often used because it fully separates the roof from the wall; without a joint, roof-to-wall flashings are a frequent source of leaks.3

Insulation, air and vapour control

The joint opening is filled with compressible insulation, and a flexible vapour retarder is carried over the vertical nailer into the opening to hold it in place. Without insulation, condensation can form on the cold joint cover and drip into the building.2 The air barrier must be continuous through the joint, so that the flexible connection is watertight, airtight and free from heat loss.1

Design and detailing rules

  • The joint must run the full width of the roof area and terminate properly at walls and edges; joints that stop short fail.2
  • Expansion joints must never be used as drainage paths, and drains should be planned so that the raised joint does not trap water. Area dividers likewise restrict water flow, so drain placement must be coordinated with them.2
  • Covers and flashings should be compatible with the roof membrane, and transitions at corners, tees and crosses are best factory-fabricated.5

Performance, maintenance and failure modes

Common problems include membrane splits where joints are missing or not raised; leaks at the cover seams, which are often sealed with uncured or semi-cured EPDM patches that can tear, peel or need replacing every 10 to 15 years; adhesive failure on irregular cover surfaces; condensation where insulation is missing; and openings at joints that stop short of the roof edge.23 Because prefabricated covers can fail faster than the surrounding roof, curbed joints may leak more often than low-profile ones, and expansion joints should be a priority during roof inspections and the first place checked when a leak appears nearby.3

Sources

Reviewed 2 November 2026 · 6 sources · 6 cited inline · Editorial policy · Plain-text version · Suggest a correction

  1. Roof Joints (Volume 42, February 1995)Canadian Roofing Contractors' Association · roofingcanada.com
  2. Details: expansion jointsBuilding Enclosure · buildingenclosureonline.com
  3. Roof Expansion Joints ExplainedRoofOnline · roofonline.com
  4. VA Master Construction Specification 07 71 00 Roof SpecialtiesU.S. Department of Veterans Affairs / WBDG · wbdg.org
  5. Expand-O-Flash Expansion Joint Cover technical data sheetJohns Manville (via RCABC) · rpm.rcabc.org
  6. RPS Expansion & Wall Curb System, Series EC-4A&BRoof Products and Systems (via Sweets) · sweets.construction.com

From the community

Know this topic first-hand? Share a photo you took, a correction with a source, or local knowledge. Every contribution is reviewed before it appears.

Contribute to Roof Expansion Joint

Loading…